Step 1 - Building Embodied Carbon Intensity - Baseline Calculation:
Calculate the building embodied carbon intensity baseline (bECI
b) for the project:
- Use materials embodied carbon intensity baselines (mECIb) published by the University of Washington/Carbon Leadership Forum or other approved data provider to calculate the embodied carbon for materials used in the project.
- The following materials must be included if they are used on the project:
- Concrete (ready mixed concreteslurryshotcrete)
- Masonry (CMU)
- Steel (rebarsteel wire and meshplate steelstructural steelsteel deckingcold formed steelopen-web steel joists)
- Aluminum (aluminum extrusionsthermally improved aluminum extrusions)
- Wood & Composites (dimensional lumberplywood/OSB sheathingglass mat gypsum sheathingprefabricated wood productscomposite lumbermass timber)
- Insulation (boardblanketfoamed-in-placeblown)
- Cladding (insulated metal panelmetal panel)
- Finishes:
- Gypsum Board
- Acoustical Ceiling Tiles
- Resilient Flooring
- Carpet
- Communications (data cabling)
- Bulk Materials (flat glass)
- Other materials may be included at the discretion of the project team
- To determine the mECIb for other materialsfollow supplemental credit guidance available in the LEED pilot credit library
Multiply the appropriate mECIb by the total quantity of each material used in the construction of the project.
Material quantities shall reflect the final as-built project and be consistently drawn from either 100% CD Construction Estimate100% CD BIM bill of materialsor Contractor procurement data.
Units can be quantified and calculated as IP or SI but must be consistent throughout.
Sum the individual material embodied carbon figures for all materials to calculate the bECIb.
Step 2 - Building Embodied Carbon Intensity – Verified Reduction Calculation
Utilize lower embodied carbon materials in the construction of the project and document a verified reduction in the project’s embodied carbon intensity.
- Utilizing a third party verified Environmental Product Declaration with applied UWCLF methodologydetermine the actual material embodied carbon intensity (mECIa) for the materials used in the project.
- The following materials must be included if they are used on the project:
- Concrete (ready mixed concreteslurryshotcrete)
- Masonry
- Steel (rebarsteel wire and meshplate steelstructural steelsteel deckingcold formed steelopen-web steel joists)
- Aluminum (aluminum extrusionsthermally improved aluminum extrusions)
- Wood & Composites (dimensional lumberplywood/OSB sheathingglass mat gypsum sheathingprefabricated wood productscomposite lumbermass timber)
- Insulation (boardblanketfoamed-in-placeblown)
- Cladding (insulated metal panelmetal panel)
- Finishes:
- Gypsum Board
- Acoustical Ceiling Tiles
- Resilient Flooring
- Carpet
- Communications (data cabling)
- Bulk Materials (flat glass)
- Other materials may be included at the discretion of the project team
Multiply the appropriate mECIa by the total quantity of each material used in the construction of the project.
Material quantities shall reflect the final as-built project and be consistently drawn from either the 100% CD Construction Estimate100% CD BIM bill of materialsor Contractor procurement data.
Units can be quantified and calculated as IP or SI but must be consistent throughout.
Sum the individual embodied carbon figures for all materials to calculate the actual building embodied carbon intensity (bECIa).
Calculate the percent difference between the bECIb and the bECIa.
Points are awarded based on the reduction in bECIb and bECIa. as follows:
- Low range reduction (0-30%) - 1 Point
- Mid-range reduction (30+%) - 2 Points
Provide Building Embodied Carbon Intensity (bECI) Report including the following:
- Material embodied carbon intensity baselines (mECIb)
- Actual material embodied carbon intensities (mECIa) for all included material categories as a table.
- Building Embodied Carbon Intensity Baseline (bECIb)
- Actual building embodied carbon intensity (bECIa)
- State the year of the baseline and actual carbon intensity data sets.
- If using an existing building vs demolishing and re-building: Create a baseline new construction building embodied carbon intensity limit by taking assumed and reasonable new construction material quantities multiplied by material embodied carbon intensity limits. Create project verified building embodied carbon intensity with as constructed quantities of materials for renovation.
Submittals
General
Register for the pilot credit
Feedback Survey
Documentation/Compliance
Step 1:
Complete calculations per below to create building embodied carbon intensity baseline (bECI
b). Units can be quantified and calculated as IP or SI but must be consistent throughout.
[view:embed_resource==12704422]
Step 2:
Complete calculations per below to create actual building embodied carbon intensity (bECI
a). Units can be quantified and calculated as IP or SI but must be consistent throughout.
[view:embed_resource==12704471]
Step 3:
Complete calculations per below to assess achieved project embodied carbon reduction.
[view:embed_resource==12704482]
Step 4:
Submit calculations per the above in table format or using third party tool that utilizes mECI
b v2021 methodology.
Submit documentation that supports the declared actual material embodied carbon intensities (mECI
a’s) and material quantities used in calculations.
- Compliant documentation includes:
- Material Quantities: 100% CD estimateexported BIM material quantities bill of materialsas-procured material quantities.
- Material Embodied Carbon Intensities: Third Party Verified EPDs for materials included in above listed Material Categories with mECIb v2021 methodology applied to address EPD variability and lack of transparency. Industry average EPDs with mECIb v2021 methodology applied are acceptable if manufacturer specific EPDs are unavailablewith additional documentation of advocacy to manufacturers asking for product specific EPDs.
APPENDIX
- UW CLF Material Category Reports v2019including material embodied carbon limits and associated methodology.
- User Guide to utilizing the free and open source Embodied Carbon in Construction Calculator (EC3) for demonstrating LEED compliance.
Changes
- 11/11/2019 - Original Publication
- 07/15/2022 - Updated product and material categories and CLF baselines